Of all the worries homeowners raise before going solar, one comes up more than almost any other: “Won’t it make my roof leak?” It’s a fair concern, especially in South Delhi’s older houses where the terrace has been waterproofed once and left alone for years. On 18 November 2026, Thermosun completed a 5kW rooftop solar installation at E-127, Greater Kailash Part 3, and the photo shows exactly how a frame can stand on a terrace without disturbing it — the steel columns rest on solid concrete plinths rather than being punched through the roof. Here’s what to know before anyone drills into yours.
Project Overview & Highlights
This Greater Kailash installation uses a tall braced galvanized steel frame over an open terrace, with the roof’s existing pipework, tank and dishes left undisturbed beneath. Here’s exactly what was delivered:
Worried Solar Will Damage Your Terrace?
It’s the most common hesitation we hear. A free site survey from a solar installation company Delhi homeowners trust looks at your roof’s waterproofing, drainage and structure before anything is quoted.
📞 Call Now 📄 Free Site SurveyWill Solar Make My Roof Leak? How a Frame Is Fixed Safely
🏠 Short Answer
Not if it’s done properly. Leaks linked to solar almost always come from careless drilling through waterproofing without resealing, or from structures that block drainage — not from the panels themselves. Both are avoidable.
The weak point of any roof is wherever something penetrates the waterproofing. So the question to ask your installer is simple: how is the frame fixed to my roof, and what happens to the waterproofing at each fixing point? A good installation follows a few principles:
✅ What a Roof-Safe Installation Looks Like
- Concrete plinths under the columns. As in this photo, the steel columns stand on solid concrete bases that spread the load across the slab and give the frame a stable footing, rather than each column being driven straight into the terrace.
- Treating the base. Where a plinth or anchor meets the slab, the area is sealed and waterproofed so water can’t track in around it.
- Keeping the drainage free. The frame, plinths and any equipment shouldn’t block the roof’s slope or outlets. Standing water near a plinth is how small problems start.
- Waterproof first if needed. If the terrace’s waterproofing is old or cracked, it’s far better to renew it before the frame goes up than to do it around the columns afterwards.
- A sensible load. A solar frame adds a modest weight per square metre, typically a small fraction of what an RCC roof is designed to carry. For older or extended buildings, a quick structural check confirms it.
- A look after the first monsoon. A quick inspection of the plinth bases after the first heavy rains catches any issue early, while it’s still easy to fix.
This is also why a tall, open frame is often the right choice on a terrace like this one. It keeps the roof surface below free, lets water flow and the surface dry out, and leaves the space usable for the household — the existing tank, dishes and pipework stay exactly where they were. That’s the standard we bring to every rooftop solar installation Delhi homes ask us about: protect the roof first, then put power on it.
Sungrow Inverter — DC/AC Setup Explained
This 5kW system runs on a Sungrow grid-tied string inverter, mounted on the wall between a DC panel box on the panel side and an AC panel box on the grid side, with conduit-protected wiring and a heavy-duty cable dropping down the wall. A compact fire extinguisher is fixed alongside the equipment.
Net Metering With BRPL Explained
Greater Kailash falls under BSES Rajdhani Power Limited (BRPL), which covers most of South and West Delhi. After commissioning, Thermosun filed the net metering application with BRPL, coordinated the inspection, and had the bi-directional meter installed. That meter records the units you draw from the grid and the surplus your system exports separately, and BRPL nets the two off at each billing cycle — the mechanism behind the monthly savings below.
Real Savings — What This Home Now Earns
With the array generating power and net metering active through BRPL, here’s the estimated monthly financial picture for this 5kW system. Actual figures depend on consumption, season and panel cleanliness, and winter months run below summer:
| Benefit | Monthly Value | Annual Value |
|---|---|---|
| Bill Reduction via Net Metering | ₹3,000 – ₹4,500 | ₹36,000 – ₹54,000 |
| Delhi GBI (₹2/unit generated, 3–10kW slab) | ₹1,000 – ₹1,250 | ₹12,000 – ₹15,000 |
| Total Monthly Financial Benefit | ₹4,000 – ₹5,750 | ₹48,000 – ₹69,000 |
📊 Solar Subsidy for This 5kW System
Under the currently documented structure, a residential system of 3kW or above receives the ₹78,000 PM Surya Ghar central subsidy plus up to ₹78,000 in Delhi state capital subsidy (₹10,000/kW, capped at 3kW) — a combined ₹1.56 lakh. A 5kW system doesn’t raise either cap; the extra return comes from higher generation, plus the Delhi GBI on top. Delhi has also announced a revised scheme for eligible low-consumption households, but it isn’t live on the official portal yet — see our Delhi Solar Subsidy 2026 guide for what’s confirmed and what isn’t.
What Thermosun Handled — Start to Finish
- 1Site Survey & Roof Assessment Terrace condition, drainage, existing tank, pipework and dishes, and shading from the neighbouring wall assessed.
- 2Frame & Plinth Design Tall braced galvanized steel frame on concrete plinths, positioned to keep drainage and access clear.
- 3Procurement of ALMM-Approved Components Panels and Sungrow inverter sourced from the MNRE-approved list for subsidy eligibility.
- 4Panel Installation Full 5kW array mounted and wired across the raised frame.
- 5Inverter & DC/AC Panel Box Setup Sungrow inverter installed with protection devices and extinguisher, fully conduit-protected.
- 6Safety Compliance Earthing and protective wiring documented to IS standard.
- 7BRPL Inspection & Net Meter Net metering application filed, inspection coordinated, bi-directional meter installed.
- 8PM Surya Ghar & Delhi GBI Filed Complete subsidy and GBI registration submitted, bank details confirmed for DBT processing.
Greater Kailash, Chittaranjan Park & Across South Delhi — We Cover Your Area
As a solar EPC company in Delhi handling design, installation, net metering and subsidy paperwork, Thermosun serves Greater Kailash, Masjid Moth, Lajpat Nagar, Kalkaji and the wider South Delhi belt directly.
💬 WhatsApp Now 📄 Free Site SurveyWhy Choose Thermosun
A solar system is meant to last 25 years, and so is a terrace. We treat the roof as something to protect rather than something to put up with: checking waterproofing and drainage at the survey, designing the footings so the slab isn’t disturbed, and being straightforward about what a homeowner should inspect after the first monsoon. With over 1,000 installations behind us, that care for the building as well as the system is a big part of why homeowners call Thermosun the best solar company in Delhi for solar for home projects in established colonies like Greater Kailash, where the house matters as much as the panels.
More Real Installations Across Delhi
- 10kW Three-Phase Solar Installation in Sarvodaya Enclave
- 4kW Bifacial Solar Installation in South Patel Nagar
- 5kW Solar Installation in Dwarka Sector 11 — Lightning Protection Explained
- 4kW Solar Installation in Karol Bagh — Storm-Ready Structure
Frequently Asked Questions
Will rooftop solar panels make my roof leak?
Not when installed properly. Leaks usually come from drilling through waterproofing without resealing, or from structures that block drainage. A frame on sealed concrete plinths with clear drainage avoids both.
How is a solar frame fixed to the roof without damaging the waterproofing?
Commonly by standing the steel columns on concrete plinths that spread the load, with the base area sealed and waterproofed. Your installer should explain how each fixing point is protected.
Should I re-waterproof my terrace before installing solar?
If the existing waterproofing is old, cracked or leaking, yes — it’s much easier and cheaper to renew it before the frame goes up than to work around the columns later.
Will the solar structure block my terrace drainage?
It shouldn’t. A good design keeps the roof’s slope and outlets clear, and uses a raised frame so water can flow and the surface can dry beneath it.
Which DISCOM handles net metering in Greater Kailash?
Greater Kailash falls under BSES Rajdhani Power Limited (BRPL), which covers most of South and West Delhi. Net metering applications for this area go through BRPL’s system.
How much solar subsidy does a 5kW system get in Delhi?
Under the currently documented structure, a 5kW residential system receives the ₹78,000 PM Surya Ghar central subsidy and up to ₹30,000 Delhi state capital subsidy — ₹1.08 lakh combined — plus the Delhi GBI. Confirm the latest figures on the official portal before applying.
How much can a Greater Kailash household save monthly with a 5kW system?
Based on this installation, combined bill reduction and Delhi GBI income comes to roughly ₹4,000–₹5,750 per month, depending on consumption, season and panel cleanliness.
Conclusion
This Greater Kailash installation shows that going solar doesn’t mean putting your roof at risk. A tall braced frame standing on concrete plinths, drainage left clear, and the existing terrace layout untouched is how a 5kW solar system sits on a roof for 25 years without causing trouble — with correct BRPL net metering and honest subsidy paperwork completing the job. For homeowners in Greater Kailash, South Delhi or anywhere in the city who’ve held back because of leakage worries, a free site survey is the best place to see exactly how your own roof would be protected.