Most people thinking about solar look up at the roof. The smarter first look is at the electricity system inside the house. Keshav Puram and Tri Nagar are established North-West Delhi colonies where many homes have lived with the same meter, wiring and distribution board for decades — and a solar system connects to all of it. On 23 November 2026, Thermosun completed a 3kW rooftop solar installation at C7/RC130, Pocket C7, and it’s a useful example of the pre-installation checks that decide whether a solar system goes live smoothly or gets stuck for weeks waiting on paperwork or electrical fixes.
Project Overview & Highlights
This Keshav Puram installation places two array tables on one tall galvanized steel frame that spans the terrace’s water tanks, leaving the roof beneath open. Here’s exactly what was delivered:
Not Sure Your Wiring and Meter Can Handle Solar?
A good solar installation company Delhi homeowners trust checks the electrical side before quoting. A free site survey covers your roof and your meter, load and wiring together.
📞 Call Now 📄 Free Site SurveyIs Your Home’s Electrical System Ready for Solar? The Pre-Installation Check
🔌 The Short Version
A rooftop solar system feeds into your home’s existing electrical set-up and your DISCOM’s meter. If those aren’t in order — the paperwork or the hardware — the best-installed panels still can’t be switched on. That’s why we check them before anything is ordered.
Here’s the checklist we run through on a survey, and why each item matters for a rooftop solar installation in Delhi:
| What We Check | Why It Matters |
|---|---|
| Sanctioned load vs. system size | DISCOMs generally link the solar capacity you can connect to your sanctioned load. A larger system may need a load enhancement first. |
| Meter type and phase | Net metering needs a bi-directional meter, which the DISCOM installs. We confirm whether your supply is single-phase or three-phase so the right inverter is chosen. |
| Main distribution board | The solar AC output connects here. The board needs the capacity and protection devices to take it safely. |
| Existing earthing | A solar system needs proper earthing, and DISCOM inspection looks at it. Weak or missing earthing in older homes gets fixed before commissioning. |
| Wiring and service cable condition | Decades-old or damaged wiring near the connection point is a safety risk and a source of inspection delays. |
| Name on the electricity bill | The connection should be in the name of the person applying and with roof rights. A bill still in a previous owner’s name is one of the most common reasons applications stall. |
| Roof rights and documents | Ownership or roof-rights proof is needed for the PM Surya Ghar subsidy application. |
| Equipment wall | A sound, dry, ventilated wall near the distribution board for the inverter and panel boxes. |
⚠️ The Most Common Hold-Up
It’s rarely the roof. It’s usually the name on the bill not matching the owner, or a sanctioned load too low for the planned system. Both are fixable, but they take time — so it’s far better to find out at the survey than after the equipment has arrived.
Sorting these before installation is what lets a solar system go from commissioning to net-metering approval without surprises. If any of these items needs attention in your home, we tell you what, why, and roughly how long it will take — before you’ve spent anything on the solar system itself.
KSolare 5G Pro Inverter — DC/AC Setup Explained
This 3kW system runs on a KSolare 5G Pro grid-tied string inverter, mounted between a DC panel box on the panel side and an AC panel box with MCB and surge protection on the grid side, with conduit-protected wiring running along the wall and a heavy-duty cable down to the connection point.
Net Metering With TPDDL Explained
Keshav Puram and Tri Nagar fall under Tata Power Delhi Distribution Limited (TPDDL), the DISCOM covering most of North and North-West Delhi. After commissioning, Thermosun filed the net metering application through TPDDL’s system, coordinated the inspection, and had the bi-directional meter installed. That meter records the units you draw from the grid and the surplus your system exports separately, and TPDDL nets the two off at each billing cycle — the mechanism behind the monthly savings below.
Real Savings — What This Home Now Earns
With the array generating power and net metering active through TPDDL, here’s the estimated monthly financial picture for this 3kW system. Actual figures depend on consumption, season and panel cleanliness, and winter months run below summer:
| Benefit | Monthly Value | Annual Value |
|---|---|---|
| Bill Reduction via Net Metering | ₹2,200 – ₹3,200 | ₹26,400 – ₹38,400 |
| Delhi GBI (₹3/unit generated, up to 3kW slab) | ₹1,000 – ₹1,200 | ₹12,000 – ₹14,400 |
| Total Monthly Financial Benefit | ₹3,200 – ₹4,400 | ₹38,400 – ₹52,800 |
📊 Solar Subsidy for This 3kW System
Under the currently documented structure, a 3kW residential system receives the ₹78,000 PM Surya Ghar central subsidy plus up to ₹78,000 in Delhi state capital subsidy (₹10,000/kW) — a combined ₹1.56 lakh, with the Delhi GBI paying ongoing per-unit income on top. Delhi has also announced a revised scheme for eligible low-consumption households, but it isn’t live on the official portal yet — see our Delhi Solar Subsidy 2026 guide for what’s confirmed and what isn’t.
What Thermosun Handled — Start to Finish
- 1Site Survey & Electrical Check Roof layout, water tanks and shading assessed, along with the sanctioned load, meter, earthing and bill details.
- 2Frame Design Tall galvanized steel frame with two array tables, designed to span the water tanks with open space beneath.
- 3Procurement of ALMM-Approved Components Panels and KSolare inverter sourced from the MNRE-approved list for subsidy eligibility.
- 4Panel Installation Full 3kW array mounted and wired across the raised frame.
- 5Inverter & DC/AC Panel Box Setup KSolare 5G Pro installed with protection devices, fully conduit-protected.
- 6Safety Compliance Earthing and protective wiring documented to IS standard.
- 7TPDDL Inspection & Net Meter Net metering application filed, inspection coordinated, bi-directional meter installed.
- 8PM Surya Ghar & Delhi GBI Filed Complete subsidy and GBI registration submitted, bank details confirmed for DBT processing.
Keshav Puram, Tri Nagar & Across North-West Delhi — We Cover Your Area
As a solar EPC company in Delhi handling design, installation, net metering and subsidy paperwork, Thermosun serves Keshav Puram, Shalimar Bagh, Pitampura, Rohini and the wider TPDDL belt directly.
💬 WhatsApp Now 📄 Free Site SurveyWhy Choose Thermosun
The dull parts of a solar project — the meter, the sanctioned load, the name on the bill — are where timelines are won or lost. We check them first, tell you plainly what needs fixing, and handle the DISCOM side so you don’t have to. With over 1,000 installations behind us, that thoroughness is a large part of why homeowners across North-West Delhi call Thermosun the best solar company in Delhi for solar for home projects in older colonies, where the building’s electrical history matters as much as its roof.
More Real Installations Across Delhi
- 3kW Solar Installation in Mukundpur, North Delhi
- 4kW Solar Installation in Samaypur — Does Solar Work in a Power Cut?
- 3kW Solar Installation on Jagatpur Road, North Delhi
- 5kW Solar Installation in Kamla Nagar — Winter Shadows Explained
Frequently Asked Questions
What does my house need before I can install rooftop solar?
A regular electricity connection in the applicant’s name, a sanctioned load suited to the planned system, a sound distribution board and earthing, roof rights, and a suitable roof. A survey checks all of these.
My electricity bill is in a previous owner’s name — can I still apply?
It’s best to get the connection transferred to your name first. A mismatch between the bill and the applicant is one of the most common reasons solar applications get delayed.
Does my sanctioned load limit the size of solar I can install?
DISCOMs generally link the permitted solar capacity to your sanctioned load. If the system you want exceeds it, a load enhancement may be needed first — your installer should check this at the survey.
Do I need to change my meter for net metering?
Net metering needs a bi-directional meter, which your DISCOM installs once your system is inspected and approved. Your installer coordinates this.
Which DISCOM handles net metering in Keshav Puram and Tri Nagar?
Keshav Puram and Tri Nagar fall under Tata Power Delhi Distribution Limited (TPDDL), which covers most of North and North-West Delhi. Net metering applications for this area go through TPDDL’s system.
How much solar subsidy does a 3kW system get in Delhi?
Under the currently documented structure, a 3kW residential system receives the ₹78,000 PM Surya Ghar central subsidy and up to ₹30,000 Delhi state capital subsidy — ₹1.08 lakh combined — plus the Delhi GBI. Confirm the latest figures on the official portal before applying.
How much can a Keshav Puram household save monthly with a 3kW system?
Based on this installation, combined bill reduction and Delhi GBI income comes to roughly ₹3,200–₹4,400 per month, depending on consumption, season and panel cleanliness.
Conclusion
This Keshav Puram installation shows that a smooth solar project is decided as much inside the house as on the roof. Checking the sanctioned load, meter, earthing and the name on the bill first, then building a tall frame over the water tanks and filing correctly with TPDDL, is what turns a 3kW solar system into a quick, hassle-free commissioning. For homeowners across Keshav Puram, Tri Nagar and North-West Delhi — especially in older colonies with long-standing connections — a free site survey that covers both the roof and the electrical set-up is the best place to start.